Thi-Qar oil fields department staffs in coordination with other company’s
department are still working to
achieve and complete the gas separation station and as follows:-
1-
Separations (rate of complete works 98%)
2- Flares system (rate of complete works 60%)
3-
Buildings :-
a- the control building
b- the electricity building
c- Water desalination system(R.O.)
The rate of completion of the above is (40%)
4-
station tanks
• fire extinguishing tank capacity(1000m³)
• flowing tanks capacity (2500m³)
• the test tanks capacity (700m³)
completion works rate (35%)
5-Wells
Rehabilitation and to Nassiriyah well /4 and drilling by Arab well logging
Co.(AWLCO )and to Distant 28m opposite to Mushref layer to depth
between(2002-2048) then opening for cleaning
6-Roads
the work is still in progress to The road relating the station ,the rate of
completion is (25%)
7- referring the main oil drain pipe, length 42 km diameter (12") to the Oil
Projects Company .in the limited time despite the difficulties where start
by work
The company is seeking through its Director the Expert Jabbar Allaibi and
engineering and technical staffs to complete the project on time despite the
difficulties .
1 – Farness of the station from the main street
2 - Objections and intervention by the tribal people of the area
3-bad weather within the area in which station is located , dust and sand
storms along days of the year.