Thi-Qar oil fields department staffs in coordination with other company’s department are still working to
achieve and complete the gas separation station and as follows:-
1- Separations (rate of complete works 98%)

2- Flares system (rate of complete works 60%)

3- Buildings :-
a- the control building
b- the electricity building
c- Water desalination system(R.O.)
The rate of completion of the above is (40%)


4- station tanks
• fire extinguishing tank capacity(1000m³)
• flowing tanks capacity (2500m³)
• the test tanks capacity (700m³)
completion works rate (35%)
5-Wells
Rehabilitation and to Nassiriyah well /4 and drilling by Arab well logging Co.(AWLCO )and to Distant 28m opposite to Mushref layer to depth between(2002-2048) then opening for cleaning
 

 

 

 

 

 



6-Roads
the work is still in progress to The road relating the station ,the rate of completion is (25%)
7- referring the main oil drain pipe, length 42 km diameter (12") to the Oil Projects Company .in the limited time despite the difficulties where start by work
The company is seeking through its Director the Expert Jabbar Allaibi and engineering and technical staffs to complete the project on time despite the difficulties .
1 – Farness of the station from the main street
2 - Objections and intervention by the tribal people of the area
3-bad weather within the area in which station is located , dust and sand storms along days of the year.
                                                                                                                                                                                                                                                                                           HOME

pressure for flowing

500 p/in²    

 closed pressure

1600 p/in² 

Productivity    4000 barrels /day